Police
| case study | Lancashire Constabulary |
| Architect/Design Team | Lancashire Constabulary |
| QS | Frank Whittle Partnership |
| Duration | 26 Weeks |
| Completion | September 2008 |
| Value | £1.5m |
Contractor designed elements in this project comprised the mechanical and electrical engineering services and pre-cast beam and block floors.
The project necessitated the complete stripping of all partitions, floors, services and finishings to get back to structure. Ground floor partitions were constructed in blockwork and first floor partitions constructed in metal stud with suspended ceilings throughout.
The contractor designed mechanical and electrical installations were state of the art including sophisticated security systems, alarms and lighting. All joinery items were manufactured to the highest standards including fixed furniture and reception desks most of which were manufactured in our own joinery workshop.
A fifty space car park was created including soiled and planted areas, externally the building was treated to a complete upgrade with polyester powder coated aluminium windows and curtain walling, new rainwater systems and sections of cladding and infill masonry.
The result was a pleasing, light, spacious working environment.